Clock Tower

A contractor will continue removing broken pieces of sidewalk from around the clock tower and pouring new concrete. The concrete sidewalk repair work is expected to be completed by Friday, Oct, 27. The work areas will be taped off, but foot traffic should still be able to move through the area. We are also hoping to start repairs to the clock tower in the near future as well.

Various Sidewalk Repairs

Once the sidewalk repairs are completed around the clocktower, the contractor will be moving to a few additional locations on campus to continue sidewalk repairs. Sidewalk repairs will occur on both sides of the Administration building adjacent to the parking lot, in front of the Campus Center, and near the entrance of the Bulmer Telecommunications Center. The work areas will again be taped off, but foot traffic will still be able to move through these areas.

Parking Garage

Due to rain, the closures of the 4th and 5th levels of the parking garage were extended to Monday, Oct. 23.