A contractor will be continue making various repairs to the sidewalks on campus for the next few weeks.

Beginning on Tuesday, Oct. 31, the contractor will be removing broken pieces of sidewalk in between the entrance to the Bulmer Telecommunications Building and parking lots B & C. The contractor will also be removing broken pieces of sidewalk in between the Administration Building and parking lots D & E.

For the remainder of the week, after the above locations of broken sidewalk are removed, the contractor will remove multiple pieces of broken sidewalk in between the entrance to the Siek Campus Center and Guenther Enrollment Services Center.

The contractor is expected to pour concrete to replace the broken sidewalk pieces at BTC, ADM and CTR on Wednesday, Nov. 8.

On Thursday Nov. 9, the contractor is expected to begin working on the broken concrete in the paver circle areas on either side of the Administration Building near the parking lots. This work is expected to take one to two weeks.